Which activity can trigger an automatic availability check for the components of a production order?

The correct answer is C. Order release. See the full explanation below for the reasoning.

Question

Which activity can trigger an automatic availability check for the components of a production order?

Options

  • AGoods receipt for a missing part
  • BMaterial staging
  • COrder release
  • DOrder rescheduling

How the community answered

(60 responses)
  • A
    12% (7)
  • B
    2% (1)
  • C
    82% (49)
  • D
    5% (3)

Community Discussion