SAP
C_TSCM42_65 · Question #102
Which activity can trigger an automatic availability check for the components of a production order?
The correct answer is C. Order release. See the full explanation below for the reasoning.
Question
Which activity can trigger an automatic availability check for the components of a production order?
Options
- AGoods receipt for a missing part
- BMaterial staging
- COrder release
- DOrder rescheduling
How the community answered
(60 responses)- A12% (7)
- B2% (1)
- C82% (49)
- D5% (3)