C_TSCM42_65 · Question #101
You maintained the planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months you have planned requirements with requirement type LSF…
The correct answer is A. You can enter the strategy group 40 in the material master and change the present requirement D. You can enter the strategy group 40 in the material master, but the requirement type is not changed. See the full explanation below for the reasoning.
Question
You maintained the planning strategy group 10 (make-to-stock production) in the material master (SAP ECC) of a material. For the coming months you have planned requirements with requirement type LSF (derived from the main strategy 10). Now, you want to change the requirement type from LSF to VSF (in accordance with planning strategy 40, planning with final assembly) for requirements in the existing production plan. Which of the following statements are applicable in this case? (Choose two)
Options
- AYou can enter the strategy group 40 in the material master and change the present requirement
- BYou must change the requirement type for planning strategy 10 to VSF in Customizing. The requirement
- CYou can change the strategy group from 10 to 40 for the existing production plan in the material master,
- DYou can enter the strategy group 40 in the material master, but the requirement type is not changed
How the community answered
(29 responses)- A76% (22)
- B7% (2)
- C17% (5)
Community Discussion
No community discussion yet for this question.