SAP
C_TSCM42_65 · Question #77
Which functions lead to a reduction in the capacity requirement for an individual operation at a work center? (Choose three.)
The correct answer is C. Setting the status technically complete (TECO) D. Confirming the operation E. Reducing the order quantity. See the full explanation below for the reasoning.
Question
Which functions lead to a reduction in the capacity requirement for an individual operation at a work center? (Choose three.)
Options
- ARescheduling the operation
- BPosting the goods receipt for the production order
- CSetting the status technically complete (TECO)
- DConfirming the operation
- EReducing the order quantity
How the community answered
(17 responses)- A18% (3)
- B6% (1)
- C76% (13)
Community Discussion
No community discussion yet for this question.