The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account: planned orders…
The correct answer is A. Differentiated assignment of two different checking rules in check control. See the full explanation below for the reasoning.
Question
The company you advise wants to control the availability check in so that when a production and/or process order is created, the following receipts or issues are taken into account: planned orders, purchase orders, production orders, reservations, dependent requirements. When the production and/or process order is released, only the stock that is currently freely usable should be taken into consideration. How can you fulfill this request?
Options
- ADifferentiated assignment of two different checking rules in check control.
- BActivate the freely usable stock in the scope of check.
- CEnter an appropriate availability checking group in the material master.
- DEnter an appropriate availability checking rule in the order type.
How the community answered
(63 responses)- A73% (46)
- B5% (3)
- C16% (10)
- D6% (4)