Which functions can be triggered before releasing a production order? (Choose three)
The correct answer is B. Selection of a routing C. Scheduling E. Selection of a BOM. See the full explanation below for the reasoning.
Question
Which functions can be triggered before releasing a production order? (Choose three)
Options
- AConfirmation
- BSelection of a routing
- CScheduling
- DStock determination
- ESelection of a BOM
How the community answered
(56 responses)- A13% (7)
- B80% (45)
- D7% (4)