For which of the following objects can you enter a confirmation? (Choose two)
The correct answer is A. Production order B. Production order operation. See the full explanation below for the reasoning.
Question
For which of the following objects can you enter a confirmation? (Choose two)
Options
- AProduction order
- BProduction order operation
- CTrigger Point
- DWork Center
How the community answered
(40 responses)- A78% (31)
- C8% (3)
- D15% (6)
Community Discussion