C_TSCM42_65 · Question #96

In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data: - Start: 7:00:00 a.m. - End: 3:00:00 p.m. - Break duration: 1 hour - Rate of…

The correct answer is C. 5.6 hours. See the full explanation below for the reasoning.

Question

In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:

  • Start: 7:00:00 a.m.
  • End: 3:00:00 p.m.
  • Break duration: 1 hour
  • Rate of utilization: 80%
  • Overload: 110%
  • Number of individual capacities: 1

How large is the standard available capacity?

Options

  • A7 hours
  • B6.16 hours
  • C5.6 hours
  • D8 hours

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    20% (7)
  • C
    71% (25)
  • D
    3% (1)