In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data: - Start: 7:00:00 a.m. - End: 3:00:00 p.m. - Break duration: 1 hour - Rate of…
The correct answer is C. 5.6 hours. See the full explanation below for the reasoning.
Question
In SAP ECC, you calculate the standard available capacity for a work center capacity using the following data:
- Start: 7:00:00 a.m.
- End: 3:00:00 p.m.
- Break duration: 1 hour
- Rate of utilization: 80%
- Overload: 110%
- Number of individual capacities: 1
How large is the standard available capacity?
Options
- A7 hours
- B6.16 hours
- C5.6 hours
- D8 hours
How the community answered
(35 responses)- A6% (2)
- B20% (7)
- C71% (25)
- D3% (1)