C_TSCM42_65 · Question #98
When modeling in-house production using SAP ECC, on which business levels can you create a bill of material (BOM)? (Choose two)
The correct answer is A. At the client level B. At the plant level. See the full explanation below for the reasoning.
Question
When modeling in-house production using SAP ECC, on which business levels can you create a bill of material (BOM)? (Choose two)
Options
- AAt the client level
- BAt the plant level
- CAt the company code level
- DAt the business area level
How the community answered
(32 responses)- A72% (23)
- C9% (3)
- D19% (6)
Community Discussion
No community discussion yet for this question.