SAP
C_TSCM42_65 · Question #89
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of…
The correct answer is B. Multi-level single-item planning with the "simulation mode" option. See the full explanation below for the reasoning.
Question
When analyzing the SAP ECC order report for a planned order for a finished product, you discover that one of the assemblies will not be available in time for the scheduled final assembly because of automatic forward scheduling. Which planning procedure do you use to create a feasible production plan from a requirements planning perspective?
Options
- AInteractive single-item planning for the delayed assembly
- BMulti-level single-item planning with the "simulation mode" option
- CTotal planning online
- DMulti-level single-item planning with the "display material list" option
How the community answered
(38 responses)- A11% (4)
- B79% (30)
- C3% (1)
- D8% (3)
Community Discussion
No community discussion yet for this question.