- Question #101Risk Management
Risk event probability is defined as:
risk probabilityrisk eventquantitative riskrisk definition - Question #102Project Planning
You've been assigned as a project manager on a research and development project for a new dental procedure. You're working in the Scope Planning process. What is the purpose of the...
scope management planscope planningscope developmentproject scope - Question #103Project Control
What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?
schedule constraintsfixed datesresource loadingidle resources - Question #104Project Control
The ability to achieve cost savings is inversely proportional to _____. ISEB ISEB-PM1 Exam
cost savingsearned valuecost performanceproject control - Question #105Organizational Aspects of Project Management
The strong matrix versus a weak matrix.
strong matrixweak matrixorganizational structureproject office - Question #106Resource Management
According to Herzberg, which of the following is a motivational factor?
Herzbergmotivational factorshygiene factorsachievement motivation - Question #107Project Planning
The scope of a project can be expected to change if:
scope changeproject scopescope creep causesproject definition - Question #108Project Control
Work authorization forms are needed in order to:
work authorizationfund releaseaudit trailproject control - Question #109Project Control
Cost management includes processes that are required to maintain financial control of projects. These processes may include:
cost managementcost estimatingcost forecastingfinancial control - Question #110Communication Management
Communication plays a major role in:
communicationorganizingcontrollingplanning - Question #111Project Control
A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000?
BACmanagement reservecontingency reserveproject funding - Question #112Project Planning
You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the project scope statement for your new Natural Bug Busters project....
scope statementchange controldeliverablesstakeholder management - Question #113Quality Management
Control chart theory is based on the differentiation of the causes of variations in quality. Variations may be produced by assignable causes. All of the following are examples of a...
control chartsassignable causesquality variationstatistical process control - Question #114Communication Management
The basic elements of communication include:
communication modelencodingdecodingfeedback - Question #115Organizational Aspects of Project Management
Life seems to be going very well for your close friend, a fellow PMP. She has taken a trip to France, bought a new car, and stocked her wine cellar with a half dozen expensive bott...
professional ethicsconflict of interestvendor giftsPMI code of conduct - Question #116Project Control
ISEB ISEB-PM1 Exam All of the following are tools and techniques of the Contract Administration process except for which one?
contract administrationprocurementperformance reviewcontract change control - Question #117Project Control
Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:
overhead ratesindirect costscost elementsproject expenses - Question #118Resource Management
You are the project manger for Xylophone Phonics. This company produces children's software programs that teach basic reading and math skills. You are ready to assign project roles...
human resource planningroles and responsibilitiesreporting relationshipsorganizational planning - Question #119Communication Management
The process of Manage Stakeholder Expectations is part of which process?
stakeholder managementexecuting process groupstakeholder expectationsprocess groups - Question #120Project Planning
Collect Requirements is:
requirements collectionscope statementscope definitionproject scope - Question #121The Project Management Lifecycle
Which is not one of the triple constraint of a project?
triple constraintcosttimescope - Question #122Organizational Aspects of Project Management
What is one of the advantages of a functional organization?
functional organizationorganizational structurechain of commandreporting structure - Question #123Quality Management
The Japanese Quality Control (QC) Circle movement motivated its participants in many ways. Which of the following represents the most important motivation for the QC circle partici...
quality circlesQC movementcontinuous improvementorganizational motivation - Question #124The Project Management Lifecycle
The methods and techniques for determining the economic costs, the environmental impact, the economic returns, and the probability for success are called:
feasibility studieseconomic evaluationproject selectioncost-benefit analysis - Question #125Project Control
Which of the following statements is true regarding schedule variances?
schedule varianceearned value managementproject schedulingvariance analysis - Question #126Communication Management
Which is not an example of formal communication?
formal communicationinformal communicationcommunication typesproject communication - Question #127Project Control
You know that PV = 470, AC = 430, EV = 480, EAC = 500, and BAC = 525. What is VAC?
VACEACBACearned value management - Question #128Resource Management
In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
resource smoothingresource levelingproject scheduleproject costs - Question #129Project Planning
Bar charts are most appropriate for:
bar chartsGantt chartsperformance reportingscheduling tools - Question #130Communication Management
All of the following may hinder a person's ability to transmit/receive a message except:
communication barriersmessage transmissionactive listeningcommunication filters - Question #131Communication Management
The Communications Management Plan should contain the following:
communications management planreporting channelscommunication mediacommunication policy - Question #132Resource Management
A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could...
Blake-Mouton gridmanagement stylesteam relationshipsleadership - Question #133Project Planning
Which involves estimating the cost of individual work items:
bottom-up estimatingcost estimatingwork packagesproject budgeting - Question #134The Project Management Lifecycle
You are a project manager for the Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Pr...
payback periodproject selectionfinancial analysiscost-benefit analysis - Question #135Resource Management
A(n) _____ system is designed to ensure the timely availability of nonhuman resources, and includes the cost in procurement, shipping/freight, storage and loss.
materials managementinventory controlprocurementnonhuman resources - Question #136The Project Management Lifecycle
Mathematical models using linear programming, dynamic, or algorithm models are considered:
project selection methodsmathematical modelslinear programmingdecision criteria - Question #137Project Control
The purpose of configuration management is to:
configuration managementchange controlproject documentationscope control - Question #138The Project Management Lifecycle
The project charter is developed by:
project charterproject initiationsenior managementproject authorization - Question #139Organizational Aspects of Project Management
Lessons learned are most often based upon project historical records. Lessons learned can be used to:
lessons learnedhistorical recordsknowledge managementproject closure - Question #140Project Control
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower ord...
CPIearned value managementcost performance indexEVM metrics - Question #141Project Planning
A work breakdown structure is most useful for:
work breakdown structureWBStask identificationproject decomposition - Question #142The Project Management Lifecycle
You are the project manager for a top-secret software project for an agency of the United States government. Your mission-should you choose to accept it-is to complete the project...
project terminationstarvation vs integrationproject lifecycleresource reassignment - Question #143Project Planning
Define Activities is typically performed by which of the following:
define activitieswork packagesproject team responsibilitiesWBS decomposition - Question #144Quality Management
Which of the following is closest to Juran's definition of Quality:
Juranfitness for usequality definitionsquality philosophy - Question #145The Project Management Lifecycle
Which of the following MUST NOT performed in project initiation process?
project initiationproject charterscope statementinitiation process - Question #146Organizational Aspects of Project Management
You are a project manager for a software manufacturing firm. The project you've just finished created a new software product that is expected to become a number-one seller. All pre...
intellectual propertyprofessional ethicssoftware releaseconfidentiality - Question #147Resource Management
Resource leveling will often affect the project by making it:
resource levelingproject scheduleproject durationresource optimization - Question #148Project Planning
Going from Level 2 to Level 4 in the work breakdown structure will result in
WBSwork breakdown structureproject decompositionscope control - Question #149Communication Management
The role of the _____ can be invaluable in problem solving.
team rolesproblem solvinggroup dynamicsdevil's advocate - Question #150The Project Management Lifecycle
Which of the following must not performed in the project initiation process?
project initiationscope statementproject phasesinitiating process