A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a…

The correct answer is A. 1,9. You've hit your session limit · resets 10:20pm (America/New_York)

Resource Management

Question

A project manager believes that the best way to manage is to form a good, harmonious working relationship with the team, and high performance will follow. The project manager could be defined as a _____ manager.

Options

  • A1,9
  • B9,1
  • C1,1
  • D9,9
  • E5,5

How the community answered

(25 responses)
  • A
    84% (21)
  • B
    8% (2)
  • D
    4% (1)
  • E
    4% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#Blake-Mouton grid#management styles#team relationships#leadership