Which involves estimating the cost of individual work items:
The correct answer is B. Bottom up estimating. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
Which involves estimating the cost of individual work items:
Options
- AAnalogous estimating
- BBottom up estimating
- CComputerized
- DSquare foot
How the community answered
(16 responses)- A13% (2)
- B81% (13)
- D6% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#bottom-up estimating#cost estimating#work packages#project budgeting