What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?
The correct answer is A. Idle resources. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
What are you likely to see as a project progresses in a schedule with must fix dates and little or no slack?
Options
- AIdle resources
- BNegative float
- CLots of free float
- DPositive float
How the community answered
(50 responses)- A76% (38)
- B14% (7)
- C8% (4)
- D2% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#schedule constraints#fixed dates#resource loading#idle resources