BCS-ISEB
ISEB-PM1 · Question #104
The ability to achieve cost savings is inversely proportional to _____. ISEB ISEB-PM1 Exam
The correct answer is D. the earned value achieved to date. You've hit your session limit · resets 10:20pm (America/New_York)
Project Control
Question
The ability to achieve cost savings is inversely proportional to _____. ISEB ISEB-PM1 Exam
Options
- Aempowerment to the P.M.
- Bproductivity
- Cthe estimated costs to complete
- Dthe earned value achieved to date
- ENone of the other alternatives apply.
How the community answered
(25 responses)- A4% (1)
- B12% (3)
- C4% (1)
- D80% (20)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#cost savings#earned value#cost performance#project control