The strong matrix versus a weak matrix.
The correct answer is E. team members are more likely to be assigned to the project office in a strong matrix. You've hit your session limit · resets 10:20pm (America/New_York)
Organizational Aspects of Project Management
Question
The strong matrix versus a weak matrix.
Options
- Astrong matrix is more difficult to manage.
- Bthe balance of power has shifted away from the PM.
- CAll of the other alternatives apply.
- Dfunctional managers no longer has control over the technical processes.
- Eteam members are more likely to be assigned to the project office in a strong matrix
How the community answered
(38 responses)- A5% (2)
- B11% (4)
- C3% (1)
- E82% (31)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#strong matrix#weak matrix#organizational structure#project office