ISEB-PM1 · Question #105

The strong matrix versus a weak matrix.

The correct answer is E. team members are more likely to be assigned to the project office in a strong matrix. You've hit your session limit · resets 10:20pm (America/New_York)

Organizational Aspects of Project Management

Question

The strong matrix versus a weak matrix.

Options

  • Astrong matrix is more difficult to manage.
  • Bthe balance of power has shifted away from the PM.
  • CAll of the other alternatives apply.
  • Dfunctional managers no longer has control over the technical processes.
  • Eteam members are more likely to be assigned to the project office in a strong matrix

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    11% (4)
  • C
    3% (1)
  • E
    82% (31)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#strong matrix#weak matrix#organizational structure#project office