Question

You've been assigned as a project manager on a research and development project for a new dental procedure. You're working in the Scope Planning process. What is the purpose of the project scope management plan?

Options

  • AThe project scope management plan describes and documents a scope baseline to help make
  • BThe project scope management plan decomposes project deliverables into smaller units of
  • CThe project scope management plan describes how project scope will be developed and how
  • DThe project scope management plan describes how cost and time estimates will be developed