ISEB-PM1 · Question #129

Bar charts are most appropriate for:

The correct answer is B. Comparing actual to planned performance to each activity. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

Bar charts are most appropriate for:

Options

  • AShowing slack time.
  • BComparing actual to planned performance to each activity.
  • CAll of the other alternatives apply.
  • DShowing critical path dependencies.
  • EShowing which activities can be rearranged in parallel.

How the community answered

(25 responses)
  • B
    80% (20)
  • C
    4% (1)
  • D
    12% (3)
  • E
    4% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#bar charts#Gantt charts#performance reporting#scheduling tools