BCS-ISEB
ISEB-PM1 · Question #120
Collect Requirements is:
The correct answer is B. Developing a written scope statement as the basis for future project decisions. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
Collect Requirements is:
Options
- ADeveloping a plan from major stakeholders
- BDeveloping a written scope statement as the basis for future project decisions
- CPlanning project milestones
- DFormalizing acceptance of the project scope
How the community answered
(17 responses)- A6% (1)
- B76% (13)
- C12% (2)
- D6% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#requirements collection#scope statement#scope definition#project scope
Community Discussion
No community discussion yet for this question.