Collect Requirements is:

The correct answer is B. Developing a written scope statement as the basis for future project decisions. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

Collect Requirements is:

Options

  • ADeveloping a plan from major stakeholders
  • BDeveloping a written scope statement as the basis for future project decisions
  • CPlanning project milestones
  • DFormalizing acceptance of the project scope

How the community answered

(17 responses)
  • A
    6% (1)
  • B
    76% (13)
  • C
    12% (2)
  • D
    6% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#requirements collection#scope statement#scope definition#project scope