Which is not one of the triple constraint of a project?
The correct answer is C. Resources. You've hit your session limit · resets 10:20pm (America/New_York)
The Project Management Lifecycle
Question
Which is not one of the triple constraint of a project?
Options
- ACost
- BTime
- CResources
- DScope
How the community answered
(36 responses)- A3% (1)
- B8% (3)
- C72% (26)
- D17% (6)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#triple constraint#cost#time#scope