A work breakdown structure is most useful for:

The correct answer is E. A and C. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

A work breakdown structure is most useful for:

Options

  • Adetermining potential delays
  • Bdeveloping a cost estimate
  • Cscheduling the start of tasks
  • Didentifying individual tasks for a project
  • EA and C

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    14% (6)
  • C
    5% (2)
  • D
    7% (3)
  • E
    72% (31)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#work breakdown structure#WBS#task identification#project decomposition