The scope of a project can be expected to change if:
The correct answer is B. All of the other alternatives apply are possible based upon the situation. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
The scope of a project can be expected to change if:
Options
- AThe project manager must provide cost estimates without having a design concept
- BAll of the other alternatives apply are possible based upon the situation
- CThe project manager is assigned after the project is defined, and the cost and schedule are
- DA clear objective is not provided
- EOversimplification (underestimating) of the nature of the work occurs
How the community answered
(36 responses)- A17% (6)
- B72% (26)
- C3% (1)
- D6% (2)
- E3% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#scope change#project scope#scope creep causes#project definition