The scope of a project can be expected to change if:

The correct answer is B. All of the other alternatives apply are possible based upon the situation. You've hit your session limit · resets 10:20pm (America/New_York)

Project Planning

Question

The scope of a project can be expected to change if:

Options

  • AThe project manager must provide cost estimates without having a design concept
  • BAll of the other alternatives apply are possible based upon the situation
  • CThe project manager is assigned after the project is defined, and the cost and schedule are
  • DA clear objective is not provided
  • EOversimplification (underestimating) of the nature of the work occurs

How the community answered

(36 responses)
  • A
    17% (6)
  • B
    72% (26)
  • C
    3% (1)
  • D
    6% (2)
  • E
    3% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#scope change#project scope#scope creep causes#project definition

Community Discussion

No community discussion yet for this question.

Full ISEB-PM1 Practice