ISEB-PM1 · Question #118
You are the project manger for Xylophone Phonics. This company produces children's software programs that teach basic reading and math skills. You are ready to assign project roles…
The correct answer is C. Human Resource Planning. You've hit your session limit · resets 10:20pm (America/New_York)
Resource Management
Question
You are the project manger for Xylophone Phonics. This company produces children's software programs that teach basic reading and math skills. You are ready to assign project roles, responsibilities, and reporting relationships. Which project Planning process are you working on?
Options
- AHuman Resource Acquisition
- BAcquire Staff
- CHuman Resource Planning
- DResource Planning
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C81% (21)
- D12% (3)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#human resource planning#roles and responsibilities#reporting relationships#organizational planning