ISEB-PM1 · Question #111

A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000?

The correct answer is B. Management Contingency Reserve. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

A Project with a total funding of $70,000 finished with a BAC value of $60,000. What term can best describe the difference of $10,000?

Options

  • AManagement Overhead
  • BManagement Contingency Reserve
  • CCost Variance
  • DSchedule Variance

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    83% (20)
  • C
    8% (2)
  • D
    4% (1)

Explanation

You've hit your session limit · resets 10:20pm (America/New_York)

Topics

#BAC#management reserve#contingency reserve#project funding

Community Discussion

No community discussion yet for this question.