ISEB-PM1 · Question #112
You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the project scope statement for your new Natural Bug Busters project. A key stakeholder…
The correct answer is B. Modify the scope statement after an approved change request has been received from the. You've hit your session limit · resets 10:20pm (America/New_York)
Project Planning
Question
You are a project manager for an agricultural supply company. You have just completed and obtained sign-off on the project scope statement for your new Natural Bug Busters project. A key stakeholder has informed you that a deliverable is missing from the project scope statement. This deliverable is a critical success factor. Which of the following actions should you take?
Options
- AModify the scope statement to reflect the new deliverable.
- BModify the scope statement after an approved change request has been received from the
- CInform the stakeholder that work not stated in the scope statement is excluded from the
- DInform the stakeholder that this deliverable must be included in phase two of this project since
How the community answered
(19 responses)- B74% (14)
- C11% (2)
- D16% (3)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#scope statement#change control#deliverables#stakeholder management