- Question #910
Which are characteristics of stakeholders? 1. They are often affected by the project 2. They agree with every project objective 3. They are only/always external to the corporate or...
- Question #911
Which role represents the stakeholders who will operate the project's products after the project is complete?
- Question #912
Which PRINCE2 principle ensures that members of the project management team know what they are expected to contribute?
- Question #913
Which is a minimum requirement for applying the organization theme?
- Question #914
Which statement about time-driven controls is CORRECT?
- Question #915
How does the project plan help to support the 'manage by stages' principle?
- Question #916
Which is a factor when deciding the duration of a management stage?
- Question #917
What information about benefits management must be documented to meet the minimum requirements for applying the business case theme?
- Question #918
According to PRINCE2, why might there be more than one business case for a project?
- Question #919
What is a benefits management approach used to assess?
- Question #920
Why is the 'initiating a project' process used?
- Question #921
Which is a purpose of the 'managing a stage boundary' process?
- Question #922
Which product identifies how often stakeholders require information?
- Question #923
Which are purposes of the quality theme? 1. To implement continuous improvement during the project 2. To establish how the project will ensure that products created will be accepta...
- Question #924
What is performed as part of the recommended risk management procedure?
- Question #925
Within which integrated element does PRINCE2 set minimum requirements?
- Question #926
Which is a purpose of the 'controlling a stage' process?
- Question #927
Which is a purpose of a project brief?
- Question #928
Which role is responsible for the quality of the specialist products delivered in the project?
- Question #929
What must be included in the risk management approach, as a minimum requirement for applying the risk theme?
- Question #930
Identify the missing word in the following sentence. The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2...
- Question #931
Which is a minimum requirement for applying the change theme?
- Question #932
Why is the 'learn from experience' principle applied to a project?
- Question #933
What should the 'managing product delivery' process ensure? 1. That the planned products meet their quality criteria 2. That the stage plan is kept up to date 3. That the project b...
- Question #934
According to the 'tailor to suit the project' principle, what is the basis for effective project management?
- Question #935
Which PRINCE2 principle is being applied when tolerances are set to establish limits of authority and accountability?
- Question #936
Which describes an off-specification?
- Question #937
Which is the first task of PRINCE2's recommended approach to 'defining and analyzing the products'?
- Question #938
Which is an objective of the 'starting up a project' process?
- Question #939
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
- Question #940
Which PRINCE2 principle is being applied when tolerances are set for the three levels of plan?
- Question #941
When should the level of tailoring be defined?
- Question #942
Which is an objective of the 'initiating a project' process?
- Question #943
Identify the missing words in the following sentence. The role of [ ? ] is assigned to the project manager if it is not allocated to another person.
- Question #944
What is a supplier of a PRINCE2 project responsible for?
- Question #945
To meet the minimum requirements for applying the progress theme, when must the business justification be reviewed?
- Question #946
Which is a purpose of the 'initiating a project' process?
- Question #947
Which are objectives of the 'managing a stage boundary' process? 1. To control the link between the people managing the project and the people producing the products 2. To approve...
- Question #948
What information should be recorded in the quality register?
- Question #949
What problem may occur if projects are not aligned with corporate business strategy?
- Question #950
Which is a purpose of the plans theme?
- Question #951
What should be considered when defining the number of management stages in a project?
- Question #952
Which statements about quality assurance and project assurance are CORRECT? 1. They are both independent of the project manager 2. They are both the responsibility of the project b...
- Question #953
Which is a minimum requirement for applying the business case theme?
- Question #954
Which theme verifies that a project's products are fit for purpose?
- Question #955
Which are benefits of using PRINCE2? 1. It removes the need for activity-based planning 2. It promotes learning and continuous improvement 3. It can be applied to any type of proje...
- Question #956
Which process provides information for the project board to review a completed stage and confirm continued business justification?
- Question #957
Which are advantages of a clear end to a project? 1. No further costs will be incurred by the project 2. Project products will be transferred to operations and support 3. All benef...
- Question #958
Identify the missing words in the following sentence. The 'managing a stage boundary' process should be executed [ ? ] a management stage.
- Question #959
The application of which principle helps to define what should be included in a project?