PRINCE2-FOUNDATION · Question #911
Which role represents the stakeholders who will operate the project's products after the project is complete?
The correct answer is B. Senior user. See the full explanation below for the reasoning.
Question
Which role represents the stakeholders who will operate the project's products after the project is complete?
Options
- AExecutive
- BSenior user
- CSenior supplier
- DProject manager
How the community answered
(14 responses)- B79% (11)
- C14% (2)
- D7% (1)