nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #518

Which product, produced by the Project Manager, would contain information on 'products completed during the period'?

The correct answer is C. Highlight Report. See the full explanation below for the reasoning.

Question

Which product, produced by the Project Manager, would contain information on 'products completed during the period'?

Options

  • AProduct Status Account
  • BCheckpoint Report
  • CHighlight Report
  • DException Report

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    14% (5)
  • C
    73% (27)
  • D
    8% (3)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice