PRINCE2-FOUNDATION · Question #1054
Why does the project board review the PID during an end stage assessment?
The correct answer is C. To review summarized progress to date and decide what to do next with the project. See the full explanation below for the reasoning.
Question
Why does the project board review the PID during an end stage assessment?
Options
- ATo confirm that project controls are adequate for the remainder of the project
- BTo notify the commissioning organization that the project has been authorized
- CTo review summarized progress to date and decide what to do next with the project
- DTo ensure that post-project reviews of operational performance are planned
How the community answered
(48 responses)- A15% (7)
- B4% (2)
- C73% (35)
- D8% (4)