Identify the missing words in the following sentence. The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
The correct answer is D. a team manager. See the full explanation below for the reasoning.
Question
Identify the missing words in the following sentence. The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.
Options
- Aproject assurance
- Bthe project board
- Cthe corporate, programme management or the customer
- Da team manager
How the community answered
(50 responses)- A10% (5)
- B4% (2)
- C4% (2)
- D82% (41)