PRINCE2-FOUNDATION · Question #1053

Identify the missing words in the following sentence. The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

The correct answer is D. a team manager. See the full explanation below for the reasoning.

Question

Identify the missing words in the following sentence. The 'managing product delivery' process provides a controlled link between [ ? ] and a project manager.

Options

  • Aproject assurance
  • Bthe project board
  • Cthe corporate, programme management or the customer
  • Da team manager

How the community answered

(50 responses)
  • A
    10% (5)
  • B
    4% (2)
  • C
    4% (2)
  • D
    82% (41)

Community Discussion

No community discussion yet for this question.