PRINCE2-FOUNDATION · Question #1052
Which are purposes of the 'directing a project' process? 1. To enable the project board to be accountable for a project's success by making key decisions 2. To enable the project board to authorize…
The correct answer is D. 1 and 4. See the full explanation below for the reasoning.
Question
Which are purposes of the 'directing a project' process? 1. To enable the project board to be accountable for a project's success by making key decisions 2. To enable the project board to authorize work packages 3. To enable the project board to prepare the communication management approach 4. To enable the project board to exercise overall control of a project
Options
- A1 and 2
- B2 and 3
- C3 and 4
- D1 and 4
How the community answered
(52 responses)- A6% (3)
- B15% (8)
- C8% (4)
- D71% (37)