PeopleCert
PRINCE2-FOUNDATION · Question #1051
Which describes a time-driven control?
The correct answer is B. The expected frequency of progress reports specified in a work package. See the full explanation below for the reasoning.
Question
Which describes a time-driven control?
Options
- AThe dates for the project's end stage assessment included in the project plan
- BThe expected frequency of progress reports specified in a work package
- CThe expected dates for planned checks of specialist products included in a stage plan
- DThe planned exception assessment meeting to authorize a requested exception plan
How the community answered
(31 responses)- A6% (2)
- B74% (23)
- C16% (5)
- D3% (1)
Community Discussion
No community discussion yet for this question.