PRINCE2-FOUNDATION · Question #1051

Which describes a time-driven control?

The correct answer is B. The expected frequency of progress reports specified in a work package. See the full explanation below for the reasoning.

Question

Which describes a time-driven control?

Options

  • AThe dates for the project's end stage assessment included in the project plan
  • BThe expected frequency of progress reports specified in a work package
  • CThe expected dates for planned checks of specialist products included in a stage plan
  • DThe planned exception assessment meeting to authorize a requested exception plan

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    74% (23)
  • C
    16% (5)
  • D
    3% (1)