Which management level should approve a course of action if project-level tolerance is exceeded?
The correct answer is A. Corporate, programme management or the customer. See the full explanation below for the reasoning.
Question
Which management level should approve a course of action if project-level tolerance is exceeded?
Options
- ACorporate, programme management or the customer
- BProject board
- CProject manager
- DTeam manager
How the community answered
(18 responses)- A72% (13)
- B17% (3)
- C6% (1)
- D6% (1)