PRINCE2-FOUNDATION · Question #1050

Which management level should approve a course of action if project-level tolerance is exceeded?

The correct answer is A. Corporate, programme management or the customer. See the full explanation below for the reasoning.

Question

Which management level should approve a course of action if project-level tolerance is exceeded?

Options

  • ACorporate, programme management or the customer
  • BProject board
  • CProject manager
  • DTeam manager

How the community answered

(18 responses)
  • A
    72% (13)
  • B
    17% (3)
  • C
    6% (1)
  • D
    6% (1)