PeopleCert
PRINCE2-FOUNDATION · Question #773
PRINCE2-FOUNDATION Question #773: Real Exam Question with Answer & Explanation
The correct answer is D. Ensure that work on products is authorized and agreed with the team. See the full explanation below for the reasoning.
Question
Which is an objective of the Managing Product Delivery process?
Options
- ASign-off completed Work Packages
- BEnsure the Business Case is kept under review
- CReport progress to the Project Board
- DEnsure that work on products is authorized and agreed with the team
Community Discussion