PRINCE2-FOUNDATION · Question #944
What is a supplier of a PRINCE2 project responsible for?
The correct answer is B. Providing resources to deliver the project outputs. See the full explanation below for the reasoning.
Question
What is a supplier of a PRINCE2 project responsible for?
Options
- AProviding the project mandate
- BProviding resources to deliver the project outputs
- CEstablishing the project's governance
- DRealizing the benefits from the project
How the community answered
(24 responses)- A4% (1)
- B71% (17)
- C17% (4)
- D8% (2)