Question
Why is the 'initiating a project' process used?
Options
- ATo decide which project approach is suitable for the project
- BTo fully understand how the project objectives will be achieved before committing significant
- CTo produce the required work packages
- DTo enable corporate or programme management to give authorization to deliver a project