Question

Why is the 'initiating a project' process used?

Options

  • ATo decide which project approach is suitable for the project
  • BTo fully understand how the project objectives will be achieved before committing significant
  • CTo produce the required work packages
  • DTo enable corporate or programme management to give authorization to deliver a project