What is a benefits management approach used to assess?

The correct answer is A. How the project's products have performed when in operational use. https://mplaza.pm/prince2-benefits-management-approach-template/

Business Case Theme

Question

What is a benefits management approach used to assess?

Options

  • AHow the project's products have performed when in operational use
  • BThe effectiveness of the project strategies
  • CHow the project has progressed against its plans
  • DThe suitability of the project management team structure

How the community answered

(26 responses)
  • A
    73% (19)
  • B
    8% (2)
  • C
    15% (4)
  • D
    4% (1)

Explanation

https://mplaza.pm/prince2-benefits-management-approach-template/

Topics

#benefits management approach#business case#operational use#project outputs