PRINCE2-FOUNDATION · Question #919
What is a benefits management approach used to assess?
The correct answer is A. How the project's products have performed when in operational use. https://mplaza.pm/prince2-benefits-management-approach-template/
Business Case Theme
Question
What is a benefits management approach used to assess?
Options
- AHow the project's products have performed when in operational use
- BThe effectiveness of the project strategies
- CHow the project has progressed against its plans
- DThe suitability of the project management team structure
How the community answered
(26 responses)- A73% (19)
- B8% (2)
- C15% (4)
- D4% (1)
Explanation
https://mplaza.pm/prince2-benefits-management-approach-template/
Topics
#benefits management approach#business case#operational use#project outputs