The correct answer is B. The project may be in a commercial environment with a number of suppliers. See the full explanation below for the reasoning.
Question
According to PRINCE2, why might there be more than one business case for a project?
Options
- AThere may be more than one management stage in the project
- BThe project may be in a commercial environment with a number of suppliers
- CThere may be more than one work package being delivered in the project
- DThe project may be in a programme environment