According to PRINCE2, why might there be more than one business case for a project?

The correct answer is B. The project may be in a commercial environment with a number of suppliers. See the full explanation below for the reasoning.

Question

According to PRINCE2, why might there be more than one business case for a project?

Options

  • AThere may be more than one management stage in the project
  • BThe project may be in a commercial environment with a number of suppliers
  • CThere may be more than one work package being delivered in the project
  • DThe project may be in a programme environment

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    74% (23)
  • C
    16% (5)
  • D
    6% (2)