The correct answer is B. The level of risk in the project. See the full explanation below for the reasoning.
Question
Which is a factor when deciding the duration of a management stage?
Options
- AThe work packages to be delivered
- BThe level of risk in the project
- CThe cost of the stage
- DThe number of products to be produced in the project