The correct answer is B. processes. See the full explanation below for the reasoning.

Question

Identify the missing word in the following sentence. The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.

Options

  • Aactivities
  • Bprocesses
  • Cproducts
  • Dquality