Which is a purpose of the 'initiating a project' process?
The correct answer is B. To enable the project board to decide whether it is worthwhile to initiate a project. See the full explanation below for the reasoning.
Question
Which is a purpose of the 'initiating a project' process?
Options
- ATo produce a stage plan for each stage of a multi-stage project
- BTo enable the project board to decide whether it is worthwhile to initiate a project
- CTo provide a fixed point at which acceptance for the project product is confirmed
- DTo enable an organization to understand the work needed to deliver the project's products
How the community answered
(52 responses)- A10% (5)
- B83% (43)
- C6% (3)
- D2% (1)