PRINCE2-FOUNDATION Question #956: Real Exam Question with Answer & Explanation

The correct answer is D. Managing a stage boundary. See the full explanation below for the reasoning.

Question

Which process provides information for the project board to review a completed stage and confirm continued business justification?

Options

  • AControlling a stage
  • BClosing a project
  • CDirecting a project
  • DManaging a stage boundary