The correct answer is D. Managing a stage boundary. See the full explanation below for the reasoning.
Question
Which process provides information for the project board to review a completed stage and confirm continued business justification?
Options
- AControlling a stage
- BClosing a project
- CDirecting a project
- DManaging a stage boundary