Which are benefits of using PRINCE2? 1. It removes the need for activity-based planning 2. It promotes learning and continuous improvement 3. It can be applied to any type of project 4. It defines…

The correct answer is B. 2 and 3. See the full explanation below for the reasoning.

Question

Which are benefits of using PRINCE2? 1. It removes the need for activity-based planning 2. It promotes learning and continuous improvement 3. It can be applied to any type of project 4. It defines specific leadership and other interpersonal skills required

Options

  • A1 and 2
  • B2 and 3
  • C3 and 4
  • D1 and 4

How the community answered

(23 responses)
  • A
    4% (1)
  • B
    83% (19)
  • C
    4% (1)
  • D
    9% (2)