The correct answer is B. When key decisions need to be made. See the full explanation below for the reasoning.
Question
What should be considered when defining the number of management stages in a project?
Options
- AWhen the team managers are available
- BWhen key decisions need to be made
- CWhen highlight reports will be submitted
- DWhen project support will be available