Which statements about quality assurance and project assurance are CORRECT? 1. They are both independent of the project manager 2. They are both the responsibility of the project board 3. They are…
The correct answer is C. 3 and 4. See the full explanation below for the reasoning.
Question
Which statements about quality assurance and project assurance are CORRECT? 1. They are both independent of the project manager 2. They are both the responsibility of the project board 3. They are both independent from the project management team 4. They both assure that applicable standards are being used
Options
- A1 and 2
- B2 and 3
- C3 and 4
- D1 and 4
How the community answered
(26 responses)- A4% (1)
- B12% (3)
- C77% (20)
- D8% (2)