Identify the missing words in the following sentence. The 'managing a stage boundary' process should be executed [ ? ] a management stage.

The correct answer is D. at, or close to the end of. https://publications.axelos.com/Prince2Agile2015/content.aspx? showNav=true&expandNav=true&page=cros_131

PRINCE2 Processes

Question

Identify the missing words in the following sentence. The 'managing a stage boundary' process should be executed [ ? ] a management stage.

Options

  • Awhen a stage plan has been prepared for
  • Bat the beginning of
  • Cwhen all the delivery steps have been completed within
  • Dat, or close to the end of,

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    15% (6)
  • C
    7% (3)
  • D
    73% (30)

Explanation

https://publications.axelos.com/Prince2Agile2015/content.aspx? showNav=true&expandNav=true&page=cros_131

Topics

#managing a stage boundary#stage timing#management stage#PRINCE2 processes