Question
Identify the missing words in the following sentence. The 'managing a stage boundary' process should be executed [ ? ] a management stage.
Options
- Awhen a stage plan has been prepared for
- Bat the beginning of
- Cwhen all the delivery steps have been completed within
- Dat, or close to the end of,