Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

The correct answer is C. Controlling a stage. stage-process-in-prince2

PRINCE2 Processes

Question

Which process ensures focus on the delivery of a stage's products and avoids uncontrolled change?

Options

  • ADirecting a project
  • BManaging a stage boundary
  • CControlling a stage
  • DStarting up a project

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    10% (2)
  • C
    85% (17)

Explanation

stage-process-in-prince2