Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

The correct answer is B. Initiation stage plan. See the full explanation below for the reasoning.

Question

Which product is created in the 'starting up a project' process to define and confirm the scope of the project?

Options

  • AProject mandate
  • BInitiation stage plan
  • CProject initiation documentation
  • DProject brief

How the community answered

(47 responses)
  • A
    2% (1)
  • B
    77% (36)
  • C
    13% (6)
  • D
    9% (4)