Which statement about time-driven controls is CORRECT?
The correct answer is A. Time-driven controls are used for monitoring the progress of work packages and management. See the full explanation below for the reasoning.
Question
Which statement about time-driven controls is CORRECT?
Options
- ATime-driven controls are used for monitoring the progress of work packages and management
- BTime-driven controls take place when specific events happen
- CTime-driven controls are produced at the end of a stage
- DAn exception report is a time-driven control
How the community answered
(27 responses)- A70% (19)
- B7% (2)
- C4% (1)
- D19% (5)