Which is a minimum requirement for applying the organization theme?

The correct answer is D. The frequency of communication to the project's stakeholders must be documented. See the full explanation below for the reasoning.

Question

Which is a minimum requirement for applying the organization theme?

Options

  • AEach member of the project management team must have a written role description
  • BThe roles of the project management team must be combined, wherever possible
  • CThe project manager must be appointed from the supplier organization
  • DThe frequency of communication to the project's stakeholders must be documented

How the community answered

(61 responses)
  • A
    15% (9)
  • B
    5% (3)
  • C
    3% (2)
  • D
    77% (47)