According to the 'tailor to suit the project' principle, what is the basis for effective project management?

The correct answer is D. That the project method relates to the project's environment. See the full explanation below for the reasoning.

Question

According to the 'tailor to suit the project' principle, what is the basis for effective project management?

Options

  • AThat the appropriate number and type of meetings are held
  • BThat the project is divided into an appropriate number of stages
  • CThat the appropriate information is provided to make decisions
  • DThat the project method relates to the project's environment

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    10% (2)
  • C
    5% (1)
  • D
    80% (16)